What We Do
End-to-end import services — from factory sourcing to your facility's doorstep.
Full-Service Import
We identify the right manufacturer for your specifications, negotiate pricing, and manage the purchase order on your behalf.
Every order is physically inspected at the factory before shipment, with full documentation provided to you.
We handle all paperwork required for U.S. import compliance, customs clearance, and standards certification.
We coordinate sea freight, inland transport, and final delivery to your facility anywhere in the continental U.S.
How It Works
Tell us what you need. We review your specs and confirm feasibility.
We provide a detailed quote including product, shipping, and compliance costs.
Order placed with manufacturer. We monitor production milestones.
Pre-shipment inspection conducted. Full report shared with you.
Shipped, cleared customs, and delivered to your U.S. facility.
Timelines
| Distribution Transformers | 8–12 weeks |
| Large Power Transformers | 10–16 weeks |
| Dry-Type Transformers | 6–10 weeks |
| Medium Voltage Switchgear | 10–14 weeks |
| Control Panels | 8–12 weeks |
| HV Cables | 6–10 weeks |
| Busbar Systems | 8–12 weeks |
| Initial inquiry response | Within 24 hours |
| Preliminary quote | 2–3 business days |
| Detailed technical quote | 5–7 business days |
| Order confirmation | Same day |
| Production updates | Bi-weekly |
| Shipment tracking | Real-time |